Planning permission secured for the conversion of Prinknash Abbey
Finding a future for an extraordinary building in the Cotswold National Landscape.
Some planning applications start with an obvious question: can we build here? Prinknash Abbey presented a rather different one: what do you do with a vast former monastery, sitting in the Cotswold National Landscape, which has stood vacant for years?
We might have the answer; we are delighted to have secured planning permission for our client, for the conversion of the former Prinknash Abbey at Cranham, Gloucestershire, into 28 homes, together with the erection of a new Glass House and associated works.
Built between 1968 and 1972 for the Benedictine monks, the Abbey extends to around 4,500 sq m and sits within substantial grounds on the Cotswold escarpment. Finding a viable future for it was never going to be entirely straightforward, but the article below details some points of interest on our journey from a negative pre-application response to planning approval.
Responding to a challenging pre-application response
Pre-application advice is valuable, even when the answer is not the one you had hoped for. In this instance, the Council questioned whether the location was sustainable, expressed uncertainty over compliance with its countryside policy and initially considered the Abbey to be “abandoned”, rather than vacant. The latter had potentially significant implications for Vacant Building Credit and consequently the scheme’s affordable housing requirement.
There are two ways of dealing with advice like this. One is to keep changing the proposal until the difficult questions disappear. Sometimes that can be the right approach.
The other is to ask whether those concerns tell the whole planning story. And in the case of Prinknash Abbey, we concluded that they did not.
Rather than sidestepping the difficult issues, we prepared an application that confronted them: The site is in the countryside; the Abbey had been unused for many years; car travel would inevitably form part of life in this rural location; conversion would also mean changes to an unusual building. But the case we made was that planning decisions are a balance, not a checklist.
The Abbey was also a substantial existing building on previously developed land. Reusing it would deliver new homes without wholesale demolition, retain the carbon embodied within the existing structure and secure substantial investment in a vacant building. The scheme would also upgrade its energy performance and provide opportunities for landscape and biodiversity enhancement.
The application raised questions around countryside development, Vacant Building Credit, affordable housing, heritage, landscape, highways, ecology and the reuse of a substantial existing building. None could sensibly be considered in isolation. Our approach was therefore to build the planning case around the scheme as a whole, rather than allowing one adverse consideration to define it.
The NPPF changed during determination
Like any good story, this one has a plot twist. During the determination period, a new National Planning Policy Framework was published. The Officer’s Report noted that the new Framework brought a significantly stronger presumption in favour of development within settlements and, in a number of defined circumstances, outside them.
For Prinknash, NPPF (2006) Policy S5(c) was particularly pertinent. It encouraged the reuse of lawful existing buildings outside settlements where they are of permanent and substantial construction and where the benefits of conversion are not outweighed by adverse effects. The Council concluded that the Abbey met that test.
In some respects, national policy had caught up with the planning case already being advanced. Months earlier, our application had emphasised many of the same principles: making effective use of under-utilised land and buildings, housing delivery, rural reuse and avoiding unnecessary demolition.
The new Framework did not make the site’s constraints disappear. Landscape, transport, ecology and heritage still had to be addressed. What it did was provide a clearer national policy context in which those issues could be weighed against the considerable benefits of giving this building a viable future.
Vacant vs abandoned building definitions in planning
One of the more interesting arguments turned on a deceptively simple word: abandoned. The council argued that Prinknash Abbey had been abandoned. For our client, this would have an impact on the scheme’s eligibility for Vacant Building Credit. However, we set out the relevant case-law tests: physical condition, period of non-use, intervening uses and the owner’s intentions. Our evidence was that the Abbey remained in good physical condition, had been maintained, secured and insured, had no intervening uses and had an owner actively seeking a positive future for it.
The argument prevailed. The Case Officer concluded that the building was vacant but had not been abandoned, and that Vacant Building Credit applied, offsetting the affordable housing requirement. It is a useful reminder that sometimes one apparently small point of planning law can have significant implications for development viability.
Conservation through change
Heritage required an equally careful balance. The Abbey is not listed, although the Council ultimately treated it as a non-designated heritage asset, identifying particular significance in elements including the crypt chapel and stained-glass windows. The conversion would inevitably affect some of that significance.
The question was therefore not whether the building could somehow be frozen in time. It was whether change could provide the means of securing its future.
The Council ultimately concluded that it could. While acknowledging some heritage harm, it was found that this was outweighed by the benefits of retaining the Abbey, investing in its repair and restoration and securing a long-term viable use.
A new home for the stained glass
The stained-glass windows presented a particularly interesting design problem.
Rather than simply treating them as an obstacle to residential conversion, the project team developed the Glass House: a new structure to the east of the Abbey in which the stained glass can be conserved and displayed.
The planning permission specifically requires a scheme for recording, removing, conserving, storing and ultimately reinstalling the stained glass within the Glass House.
There is something rather satisfying about that solution. The Abbey can evolve without erasing the elements that make its history worth remembering and in so doing, it will secure the long term future of some really breathtaking stained-glass.
Planning balance, so much more than simply a policy argument
Ultimately, permission was not secured through one clever planning argument. The application had to address landscape, highways, ecology, drainage, residential amenity, design and heritage. Lesser Horseshoe bats were identified using part of the building, requiring appropriate mitigation, while the scheme also secured biodiversity gains and long-term habitat management.
Retaining the structure also avoids the significant embodied-carbon impacts associated with demolition and replacement construction. The development incorporates measures including solar panels and air-source heat pumps, benefits which were given substantial weight in the final planning balance.
The outcome is perhaps deceptively simple: 28 homes and a viable new chapter for a building which had been without a long-term use for years.
What can developers take from Prinknash?
Perhaps the most useful lesson, particularly for small and medium-sized developers looking at complicated brownfield or conversion opportunities, is this:
- Treat a negative pre-app as a diagnosis, not necessarily a verdict: Some objections reveal a fundamental flaw. Others identify matters that can be answered through evidence, design, specialist advice or a more complete reading of planning policy.
- Look beyond the headline objection. At Prinknash, the countryside location was a constraint, but it had to be balanced against benefits including housing delivery, reuse of an existing building, retaining embodied carbon and biodiversity enhancement.
- Interrogate matters that affect viability. The distinction between a vacant and abandoned building became particularly important because of its implications for Vacant Building Credit and affordable housing.
- Build the technical and policy cases together. The principle of development could not be considered in isolation from heritage, ecology, landscape, highways and design. The eventual permission reflects that broader planning balance.
Good planning strategy is not about pretending a site has no disadvantages. It is about understanding those disadvantages well enough to put them in their proper place in the planning balance.
At Prinknash, that meant returning repeatedly to one fairly basic question: what is the sensible long-term future of this building? Leaving around 4,500 sq m of Abbey vacant was not it. Finding a viable new use, conserving important features, improving environmental performance and delivering 28 homes proved a rather better answer.
Working with a difficult site or building?
Complex sites rarely turn on a single planning issue. If you are considering the redevelopment or conversion of an existing building and want to understand the planning strategy before committing further investment, speak to McLoughlin Planning.
At McLoughlin Planning, our focus is on achieving successful planning outcomes through clear, commercially aware advice. Our team of Chartered Town Planning Consultants provides strategic advice and planning solutions across England and Wales, working on projects ranging from strategic land promotion and commercial development to private residential schemes and rural diversification projects.
Following the acquisition of Plainview Planning in 2024, our Group now combines the expertise of 13 planning professionals and support staff. This collaboration enables us to deliver commercially minded, creative solutions to a wide range of planning challenges.
For larger, strategic or complex projects, such as land promotions, multi-phase developments or aviation schemes, our McLoughlin Planning team can provide specialist advice.
For householder projects, developments of 10 dwellings or fewer, or smaller independent commercial schemes, our dedicated Plainview Planning team offers tailored support.
If you have a development proposal that could benefit from expert planning consultancy input, you can explore our team via our About Us page or contact us through the Arrange a Call option on our contact page, or via the email address and telephone number provided below.
We value your privacy and any information you provide will remain confidential and used solely in relation to your enquiry.
As always, the content of this article was correct at the time of publication. For the most up-to-date advice on planning policy and development opportunities, please contact our team.
Nathan McLoughlin – Managing Director
T: 01242895008
E: nathan.mcloughlin@mplanning.co.uk
Project Team
Client: Dillon Enterprises
Planning: McLoughlin Planning
Architecture: O’Leary Goss Architects
Landscape: Liz Lake Associates
Ecology & BNG: Ethos
Transport: Highgate Transportation
Flood Risk, Drainage & Structures: Curtins
Arboriculture: Silverback
Lighting: DFL
IMAGE SOURCE:
Liz Lake Associates
O’learygoss Architects